Close Menu
    Facebook X (Twitter) Instagram
    TRENDING :
    • Club Coastal’s Rebrand Breaks Sales Records: $30K in 1 Day
    • 5 Signals That Influence Claude and ChatGPT Recommendations
    • This year’s FIFA World Cup is getting a new piece of equipment by Adidas
    • At Harvard, over 60% of grades given last year were A’s. Now the university is weighing a grade inflation crackdown
    • Trump and Xi Jinping wrap Beijing summit. Here’s where U.S.-China relations stand
    • Why Speed Beats Perfection in Modern Marketing — and How Fast Teams Turn Early Launches Into Outsized Growth
    • Meet Espa, a fresh take on AI assistants
    • Real Estate Absorbs Innovation — Here’s How to Stand Out
    Compatriot Chronicle
    • Home
    • US Politics
    • World Politics
    • Economy
    • Business
    • Headline News
    Compatriot Chronicle
    Home»Business»Who should pay for the power grid’s race to keep up with data centers?
    Business

    Who should pay for the power grid’s race to keep up with data centers?

    December 16, 20257 Mins Read
    Share Facebook Twitter Pinterest LinkedIn Tumblr Telegram Email Copy Link
    Follow Us
    Google News Flipboard
    Share
    Facebook Twitter LinkedIn Pinterest Email


    The amount of electricity data centers use in the U.S. in the coming years is expected to be significant. But regular reports of proposals for new ones and cancellations of planned ones mean that it’s difficult to know exactly how many data centers will actually be built and how much electricity might be required to run them.

    As a researcher of energy policy who has studied the cost challenges associated with new utility infrastructure, I know that uncertainty comes with a cost. In the electricity sector, it is the challenge of state utility regulators to decide who pays what shares of the costs associated with generating and serving these types of operations, sometimes broadly called “large load centers.”

    States are exploring different approaches, each with strengths, weaknesses, and potential drawbacks.

    A new type of customer?

    For years, large electricity customers such as textile mills and refineries have used enough electricity to power a small city.

    Moreover, their construction timelines were more aligned with the development time of new electricity infrastructure. If a company wanted to build a new textile mill and the utility needed to build a new gas-fired power plant to serve it, the construction on both could start around the same time. Both could be ready in two and a half to three years, and the textile mill could start paying for the costs necessary to serve it.

    Modern data centers use a similar amount of electricity but can be built in nine to 12 months. To meet that projected demand, construction of a new gas-fired power plant, or a solar farm with battery storage, must begin a year—maybe two—before the data center breaks ground.

    During the time spent building the electrical supply, computing technology advances, including both the capabilities and the efficiency of the kinds of calculations artificial intelligence systems require. Both factors affect how much electricity a data center will use once it is built.

    Technological, logistical, and planning changes mean there is a lot of uncertainty about how much electricity a data center will ultimately use. So it’s very hard for a utility company to know how much generating capacity to start building.

    Keeping older coal plants running may be an expensive way to generate power. Ulysse Bellier/AFP via Getty Images

    Handling the risks of development

    This uncertainty costs money: A power plant could be built in advance, only to find out that some or all of its capacity isn’t needed. Or no power plant is built, and a data center pops up, competing for a limited supply of electricity.

    Either way, someone needs to pay—for the excess capacity or for the increased price of what power is available. There are three possible groups that might pay: the utilities that provide electricity, the data center customers, and the rest of the customers on the system.

    However, utility companies have largely ensured their risk is minimal. Under most state utility-regulation processes, state officials review spending proposals from utility companies to determine what expenses can be passed on to customers. That includes operating expenses such as salaries and fuel costs, as well as capital investments, such as new power plants and other equipment.

    Regulators typically examine whether proposed expenses are useful for providing service to customers and reasonable for the utility to expect to incur. Utilities have been very careful to provide their regulators with evidence about the costs and effects of proposed data centers to justify passing the costs of proposed investments in new power plants along to whomever the customers happen to be.

    Regulators, then, are left to equitably allocate the costs to the prospective data center customers and the rest of the ratepayers, including homes and businesses. In different states, this is playing out differently.

    Kentucky’s approach to usefulness

    Kentucky is attempting to address the demand uncertainty by conditionally approving two new natural gas-fired generators in the state. However, the utility companies—Louisville Gas & Electric and Kentucky Utilities—must demonstrate that those plants will actually be needed and used. But it’s not clear how they could do that, especially considering the time frames involved.

    For instance, suppose the utility has a letter of agreement or even a contract with a new data center or other large customer. That might be sufficient proof for the regulator to approve charging customers for the costs of building a new power plant.

    But it’s not clear what would happen if the data center ends up not being built, or needing much less power than expected. If the utility can’t get the money from the data center company—because they bill customers based on actual usage—that leaves regular consumers on the hook.

    A large rectangular building.
    A data center in Columbus, Ohio, is just one of many being built or proposed around the country. Eli Hiller/For The Washington Post via Getty Images

    Ohio’s ‘demand ratchet’ and credit guarantee

    In Ohio, the major power company AEP has a specific rate plan for data centers and other large electricity customers. One element, called a “demand ratchet,” is designed to mitigate month-to-month uncertainty in electricity consumption by data centers. The data center’s monthly bill is based on the current month’s demand or 85% of the highest monthly demand from the previous 11 months—whichever is higher.

    The benefit is that it protects against a data center using huge amounts of electricity one month and very little the next, which would otherwise yield a much lower bill. The ratchet helps ensure that the data center is paying a significant share of the cost of providing enough electricity, even if it doesn’t use as much as was expected.

    This ratchet effectively locks in the data center’s payments for 12 months, but regulators might expect a longer commitment from the center. For instance, Florida’s utilities regulator has approved an agreement that would require a data center company to pay for 70% of the agreed-upon demand in their entire electricity contract, even if the company didn’t use the power.

    Another aspect of Ohio’s approach addresses the risk of changing business plans or technology. AEP requires a credit guarantee, like a deposit, letter of credit or parent company guarantee of payment, equal to 50% of the customer’s expected minimum bill under the contract. While this theoretically reduces the risk borne by other customers, it also raises concerns.

    For example, a utility may not end up signing contracts directly with a large, well-known, wealthy technology company but with a subsidiary corporation with a more generic name—imagine something like “Westside Data Center LLC”—created solely to build and operate one data center. If the data center’s plans or technology changes, that subsidiary could declare bankruptcy, leaving the other customers with the remaining costs.

    Harnessing strength in flexibility

    A key advantage of these new types of customers is that they are extremely nimble in the way they use electricity.

    If data centers can make money based on their flexibility, as they have in Texas, then a portion of those profits can be returned to the other customers that shared the investment risk. A similar mechanism is being implemented in Missouri: If the utility makes extra money from large customers, then 65% of that revenue increase is returned to the other customers.

    Change is coming to the U.S. electricity system, but nobody is sure how much. The methods by which states are trying to allocate the cost of that uncertainty vary, but the critical element is understanding their respective strengths and weaknesses to craft a system that is fair for everyone.

    Theodore J. Kury is a director of energy studies at the University of Florida.

    This article is republished from The Conversation under a Creative Commons license. Read the original article.



    Source link

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

    Related Posts

    Club Coastal’s Rebrand Breaks Sales Records: $30K in 1 Day

    May 15, 2026

    5 Signals That Influence Claude and ChatGPT Recommendations

    May 15, 2026

    This year’s FIFA World Cup is getting a new piece of equipment by Adidas

    May 15, 2026
    Top News

    Time for a CRISPR discussion about genetic engineering

    By Staff WriterNovember 26, 2025

    Changing an organism’s genome is a profound act, and the tools you use to make…

    New Year’s resolutions don’t work: Try this bingo card instead

    December 20, 2025

    Seoul And Washington Pen $950 Billion Deal

    October 31, 2025

    How to Set a Meaningful Life Goal Definition

    September 21, 2025
    Top Trending

    Club Coastal’s Rebrand Breaks Sales Records: $30K in 1 Day

    By Staff WriterMay 15, 2026

    Key Takeaways Bozigian’s business hit $100,000 in sales, driven by TikTok, during…

    5 Signals That Influence Claude and ChatGPT Recommendations

    By Staff WriterMay 15, 2026

    Opinions expressed by Entrepreneur contributors are their own. Key Takeaways Third-party corroboration…

    This year’s FIFA World Cup is getting a new piece of equipment by Adidas

    By Staff WriterMay 15, 2026

    Every four years, the men’s World Cup delivers some certainties. The pitch…

    Categories
    • Business
    • Economy
    • Headline News
    • Top News
    • US Politics
    • World Politics
    About us

    The Populist Bulletin serves as a beacon for the populist movement, which champions the interests of ordinary citizens over the agendas of the powerful and entrenched elitists. Rooted in the belief that the voices of everyday workers, families, and communities are often drowned out by powerful people and institutions, it delivers straightforward, unfiltered, compelling, relatable stories that resonate with the values of the American public.

    The Populist Bulletin was founded with a fervent commitment to inform, inspire, empower and spark meaningful conversations about the economy, business, politics, inequality, government accountability and overreach, globalization, and the preservation of American cultural heritage.

    The site offers a dynamic mix of investigative journalism, opinion editorials, and viral content that amplify populist sentiments and deliver stories that echo the concerns of everyday Americans while boldly challenging mainstream narratives that serve the privileged few.

    Top Picks

    Club Coastal’s Rebrand Breaks Sales Records: $30K in 1 Day

    May 15, 2026

    5 Signals That Influence Claude and ChatGPT Recommendations

    May 15, 2026

    This year’s FIFA World Cup is getting a new piece of equipment by Adidas

    May 15, 2026
    Categories
    • Business
    • Economy
    • Headline News
    • Top News
    • US Politics
    • World Politics
    Copyright © 2025 Populist Bulletin. All Rights Reserved.

    Type above and press Enter to search. Press Esc to cancel.